Building Progress

Left

104 days 23 hours 28 minutes 37 seconds

until delivery of first units

The construction at Avalon Estate is advancing.

T buildings 
T5: the structure, masonry, plasterboard installations, and partitions are completed. Currently work is conducted on screed and underfloor heating;
T4: the foundation has been completed;
T2, T3: work is conducted on the excavations for the foundation.

A buildings 
A1a: the structure is completed. We currently work on the exterior masonry;
A1b: the masonry is 85% completed. We are working on the plasterboard partitions;
A1c: the structure, masonry, and plasterboard partitions are completed. Also, the carpentry was installed. We are currently working on the underfloor heating.

Gatehouse 
The partitioning, screed and interior finishes are finalized. We are working on installing the final insulation on the facade.

Clubhouse 
The structure is finalized. The facade is under construction.

Access road 
In September 2021 the access road will be paved.

The first phase consisting of 254 units, out of the planned 746, will be finalized during the last quarter of this year and the beginning of 2022. The gatehouse, the residential club and 50% of the green spaces are also going to be finished.
The construction works for the interior and exterior infrastructure are going as planned, and will be delivered gradually from December 2021 until their completion in June 2022.

Discover more details about the different units in Avalon Estate from our website.